Blue Marina Residence by Shakirov Developmentsphoto: shakirovdevelopments.aeActive
Progress
5.94%
Handover
~ Oct 2027
Escrow
#0205930702705

Blue Marina Residence by Shakirov Developments

#3867 · Shakirov Developments L.L.C · Palm Deira

data last checked 17 Jul 2026

Construction progress

5.94% of construction complete · last inspected by DLD 3 Apr 2026

≈31 pts behind the planned pace as of the last inspection

today
inspected 3 Apr 2026
start 1 May 2025 est. finish 31 Oct 2027