photo: ranquilinfra.comUnder constructionBlossom 76 by Tranquil
DLD developer no. 1812 · TRANQUIL INFRA DEVELOPERS L.L.C
Deals checked 29 Oct 2026 · project details as of 27 Aug 2026
Residential Building (G+4P+16+Roof).The project designed to have a concrete structure and block with internal and external finishes.
Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 27 Oct 2026 | Sales | Off-plan | Flat · Studio | 39.37 | 424 | 651,264 | 16,542 | 1,537 |
| 7 Oct 2026 | Sales | Off-plan | Flat · Studio | 39.47 | 425 | 652,800 | 16,539 | 1,537 |
| 21 Aug 2026 | Sales | Off-plan | Flat · 1 B/R | 90.06 | 969 | 1,413,650 | 15,697 | 1,458 |
| 19 May 2026 | Sales | Off-plan | Flat · Studio | 39.47 | 425 | 658,750 | 16,690 | 1,551 |
| 15 Apr 2026 | Sales | Off-plan | Flat · Studio | 39.25 | 422 | 601,350 | 15,321 | 1,423 |
| 14 Apr 2026 | Sales | Off-plan | Show Rooms · NA | 204.35 | 2,200 | 4,620,000 | 22,608 | 2,100 |
| 9 Apr 2026 | Sales | Off-plan | Flat · 1 B/R | 90.06 | 969 | 1,356,600 | 15,063 | 1,399 |
| 9 Apr 2026 | Sales | Off-plan | Flat · Studio | 39.47 | 425 | 637,500 | 16,152 | 1,501 |
| 23 Mar 2026 | Sales | Off-plan | Flat · Studio | 39.37 | 424 | 646,600 | 16,424 | 1,526 |
| 27 Feb 2026 | Sales | Off-plan | Flat · Studio | 39.47 | 425 | 658,750 | 16,690 | 1,551 |
| 27 Feb 2026 | Sales | Off-plan | Flat · Studio | 39.47 | 425 | 648,125 | 16,421 | 1,526 |
| 27 Feb 2026 | Sales | Off-plan | Flat · 1 B/R | 89.04 | 958 | 1,365,150 | 15,332 | 1,424 |
| 25 Feb 2026 | Sales | Off-plan | Flat · 1 B/R | 89.04 | 958 | 1,341,200 | 15,063 | 1,399 |
| 13 Feb 2026 | Sales | Off-plan | Flat · Studio | 39.47 | 425 | 645,000 | 16,342 | 1,518 |
| 13 Feb 2026 | Sales | Off-plan | Flat · Studio | 39.47 | 425 | 645,000 | 16,342 | 1,518 |
Blossom 76 by Tranquil: common questions
Is Blossom 76 by Tranquil delayed?
It is behind plan. Construction was 40.01% complete at the last DLD inspection on 14 August 2026, while its registered timeline (planned completion 26 March 2027) would expect about 76% by then.
When is the handover of Blossom 76 by Tranquil?
The planned completion date registered with Dubai Land Department is 26 March 2027. Handover usually follows completion; the developer confirms the exact date.
How much of Blossom 76 by Tranquil is built?
Construction was 40.01% complete at the last DLD inspection on 14 August 2026, as published by Dubai Land Department.
Where is Blossom 76 by Tranquil located?
Blossom 76 by Tranquil is in Jumeirah Village Circle (JVC), Dubai. Dubai Land Department records it under the Al Barsha South Fourth area.
Who is the developer of Blossom 76 by Tranquil?
Blossom 76 by Tranquil is developed by TRANQUIL INFRA DEVELOPERS L.L.C (DLD developer no. 1812). It is registered with Dubai Land Department as project no. 3113, with 113 units.
Does Blossom 76 by Tranquil have an escrow account?
Yes. Dubai Land Department open data lists escrow account 001582131953401. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in Blossom 76 by Tranquil?
The most recent sale registered with Dubai Land Department was on 27 October 2026 for AED 651,264. Across the 21 recorded sales, the average was AED 1,477 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.