Binghatti Starlightphoto: binghatti.comActive
Progress
63.11%
Handover
Escrow
#0405887192008

Binghatti Starlight

#3195 · Binghatti Developers FZE · Al Jadaf · 511 units

More from Binghatti
declared value 228.9M AED data last checked 12 Sept 2026

3B + G + 3P + 20 RESIDENTIAL FLOORS + ROOF

Construction progress

63.11% of construction complete · last inspected by DLD 14 May 2026

overdue — planned finish was 31 Mar 2026, still at 63.11%

today inspected 14 May 2026
start 30 Jul 2024 est. finish 31 Mar 2026
Google · this project
4.1
23 reviews