photo: binghatti.comUnder constructionDLD developer no. 1051 · Binghatti Developers FZE
Data last checked 29 Oct 2026
More from Binghatti →5B + G + 4P + 49 RESIDENTIAL FLOORS + 2MECH + ROOF ( 3 TOWERS)
Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 20 Oct 2026 | Sales | Off-plan | Flat · Studio | 43.26 | 466 | 1,187,407 | 27,448 | 2,550 |
| 12 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 94.94 | 1,022 | 2,347,248.98 | 24,723 | 2,297 |
| 12 Oct 2026 | Gifts | Off-plan | Flat · 1 B/R | 94.94 | 1,022 | 2,900,004.58 | 30,546 | 2,838 |
| 12 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 94.94 | 1,022 | 2,507,499.15 | 26,411 | 2,454 |
| 9 Oct 2026 | Sales | Off-plan | Flat · Studio | 39.53 | 425 | 1,000,000 | 25,297 | 2,350 |
| 3 Oct 2026 | Sales | Off-plan | Flat · Studio | 42.96 | 462 | 1,277,249.22 | 29,731 | 2,762 |
| 2 Oct 2026 | Sales | Off-plan | Flat · Studio | 39.23 | 422 | 1,115,625 | 28,438 | 2,642 |
| 29 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 70.83 | 762 | 1,400,000 | 19,766 | 1,836 |
| 25 Sept 2026 | Sales | Off-plan | Flat · Studio | 41.75 | 449 | 1,000,000 | 23,952 | 2,225 |
| 22 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 78.88 | 849 | 2,039,999 | 25,862 | 2,403 |
| 21 Sept 2026 | Sales | Off-plan | Flat · Studio | 39.23 | 422 | 1,025,000 | 26,128 | 2,427 |
| 18 Sept 2026 | Gifts | Off-plan | Flat · Studio | 43.24 | 465 | 1,200,004.21 | 27,752 | 2,578 |
| 17 Sept 2026 | Gifts | Off-plan | Flat · 1 B/R | 87.16 | 938 | 2,650,000.44 | 30,404 | 2,825 |
| 11 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 77.18 | 831 | 1,905,000 | 24,683 | 2,293 |
| 10 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 77.18 | 831 | 1,625,000 | 21,055 | 1,956 |
Binghatti Skyrise: common questions
Is Binghatti Skyrise delayed?
It is behind plan. Construction was 22.4% complete at the last DLD inspection on 21 October 2026, while its registered timeline (planned completion 31 December 2026) would expect about 91% by then.
When is the handover of Binghatti Skyrise?
The planned completion date registered with Dubai Land Department is 31 December 2026. Handover usually follows completion; the developer confirms the exact date.
How much of Binghatti Skyrise is built?
Construction was 22.4% complete at the last DLD inspection on 21 October 2026, as published by Dubai Land Department.
Where is Binghatti Skyrise located?
Binghatti Skyrise is in Business Bay, Dubai.
Who is the developer of Binghatti Skyrise?
Binghatti Skyrise is developed by Binghatti Developers FZE (DLD developer no. 1051). It is registered with Dubai Land Department as project no. 3349, with 3,358 units.
Does Binghatti Skyrise have an escrow account?
Yes. Dubai Land Department open data lists escrow account 001582131526101. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in Binghatti Skyrise?
The most recent sale registered with Dubai Land Department was on 20 October 2026 for AED 1,187,407. Across the 85 recorded sales, the average was AED 2,644 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.