photo: binghatti.comDelayed 1 mo.DLD developer no. 1051 · Binghatti Developers FZE
Data last checked 29 Oct 2026
More from Binghatti →3B + G + 3P + 29 RESIDENTIAL FLOORS + 1MECH. + ROOF
Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 22 Oct 2026 | Gifts | Off-plan | Flat · Studio | 37.29 | 401 | 580,610.8 | 15,570 | 1,447 |
| 22 Oct 2026 | Sales | Off-plan | Flat · Studio | 39.38 | 424 | 1,200,000 | 30,472 | 2,831 |
| 5 Oct 2026 | Sales | Off-plan | Flat · Studio | 39.38 | 424 | 1,299,800 | 33,007 | 3,066 |
| 2 Oct 2026 | Sales | Off-plan | Flat · Studio | 39.38 | 424 | 1,100,000 | 27,933 | 2,595 |
| 9 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 77.89 | 838 | 1,909,000 | 24,509 | 2,277 |
| 9 Sept 2026 | Sales | Off-plan | Flat · Studio | 39.38 | 424 | 1,268,060 | 32,201 | 2,992 |
| 9 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 77.57 | 835 | 1,935,000 | 24,945 | 2,317 |
| 3 Sept 2026 | Sales | Off-plan | Flat · Studio | 39.38 | 424 | 1,100,000 | 27,933 | 2,595 |
| 2 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 77.89 | 838 | 1,904,000 | 24,445 | 2,271 |
| 16 Jun 2026 | Sales | Off-plan | Flat · 1 B/R | 92.28 | 993 | 2,256,000 | 24,447 | 2,271 |
| 12 Jun 2026 | Sales | Off-plan | Flat · Studio | 37.05 | 399 | 1,079,000 | 29,123 | 2,706 |
| 22 Apr 2026 | Sales | Off-plan | Flat · Studio | 37.05 | 399 | 1,071,000 | 28,907 | 2,686 |
| 22 Apr 2026 | Sales | Off-plan | Flat · Studio | 37.05 | 399 | 1,065,000 | 28,745 | 2,670 |
| 20 Apr 2026 | Sales | Off-plan | Flat · 1 B/R | 92.53 | 996 | 2,312,000 | 24,986 | 2,321 |
| 1 Apr 2026 | Sales | Off-plan | Flat · 1 B/R | 77.97 | 839 | 1,913,000 | 24,535 | 2,279 |
Binghatti Skyhall: common questions
Is Binghatti Skyhall delayed?
It is behind plan. Construction was 31.14% complete at the last DLD inspection on 30 April 2026, while its registered timeline (planned completion 31 August 2026) would expect about 79% by then.
When is the handover of Binghatti Skyhall?
The planned completion date registered with Dubai Land Department is 31 August 2026. Handover usually follows completion; the developer confirms the exact date.
How much of Binghatti Skyhall is built?
Construction was 31.14% complete at the last DLD inspection on 30 April 2026, as published by Dubai Land Department.
Where is Binghatti Skyhall located?
Binghatti Skyhall is in Business Bay, Dubai.
Who is the developer of Binghatti Skyhall?
Binghatti Skyhall is developed by Binghatti Developers FZE (DLD developer no. 1051). It is registered with Dubai Land Department as project no. 3504, with 728 units.
Does Binghatti Skyhall have an escrow account?
Yes. Dubai Land Department open data lists escrow account 9009226759924002. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in Binghatti Skyhall?
The most recent sale registered with Dubai Land Department was on 22 October 2026 for AED 1,200,000. Across the 43 recorded sales, the average was AED 2,716 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.