Binghatti Skyhallphoto: binghatti.comActive
Progress
31.14%
Handover
Escrow
#9009226759924002

Binghatti Skyhall

#3504 · Binghatti Developers FZE · Business Bay · 728 units

More from Binghatti
declared value 385.0M AED data last checked 12 Sept 2026

3B + G + 3P + 29 RESIDENTIAL FLOORS + 1MECH. + ROOF

Construction progress

31.14% of construction complete · last inspected by DLD 30 Apr 2026

≈48 pts behind the planned pace as of the last inspection

today
inspected 30 Apr 2026
start 1 Feb 2025 est. finish 31 Aug 2026