Binghatti Skybladephoto: binghatti.comActive
Progress
17.06%
Handover
~ Nov 2027
Escrow
#001582194170301

Binghatti Skyblade

#3725 · Binghatti Developers FZE · Burj Khalifa

More from Binghatti
data last checked 17 Jul 2026

Construction progress

17.06% of construction complete · last inspected by DLD 21 Apr 2026

≈26 pts behind the planned pace as of the last inspection

today
inspected 21 Apr 2026
start 1 Feb 2025 est. finish 30 Nov 2027
Google · this project
4.7
15 reviews