photo: binghatti.comUnder constructionDLD developer no. 1051 · Binghatti Developers FZE
Deals checked 29 Oct 2026 · project details as of 17 Jul 2026
More from Binghatti →Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 19 Oct 2026 | Sales | Off-plan | Flat · Studio | 48.9 | 526 | 1,969,999 | 40,286 | 3,743 |
| 12 Oct 2026 | Sales | Off-plan | Flat · Studio | 49.51 | 533 | 1,896,349.03 | 38,302 | 3,558 |
| 12 Oct 2026 | Gifts | Off-plan | Flat · Studio | 44.47 | 479 | 1,860,111 | 41,828 | 3,886 |
| 12 Oct 2026 | Gifts | Off-plan | Flat · Studio | 35.08 | 378 | 1,740,169.6 | 49,606 | 4,609 |
| 2 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 89.82 | 967 | 3,719,999 | 41,416 | 3,848 |
| 2 Oct 2026 | Sales | Off-plan | Flat · 2 B/R | 153.18 | 1,649 | 5,201,999.15 | 33,960 | 3,155 |
| 1 Oct 2026 | Sales | Off-plan | Flat · 2 B/R | 117.13 | 1,261 | 4,959,999 | 42,346 | 3,934 |
| 21 Sept 2026 | Sales | Off-plan | Flat · Studio | 49.51 | 533 | 2,014,999 | 40,699 | 3,781 |
| 17 Sept 2026 | Sales | Off-plan | Flat · 2 B/R | 115.71 | 1,245 | 5,452,749.15 | 47,124 | 4,378 |
| 11 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 89.83 | 967 | 3,272,499.15 | 36,430 | 3,384 |
| 11 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 89.81 | 967 | 3,649,999 | 40,641 | 3,776 |
| 10 Jul 2026 | Sales | Off-plan | Flat · Studio | 44.47 | 479 | 2,039,999 | 45,874 | 4,262 |
| 7 Jul 2026 | Sales | Off-plan | Flat · Studio | 48.97 | 527 | 1,984,999 | 40,535 | 3,766 |
| 3 Jul 2026 | Sales | Off-plan | Flat · 2 B/R | 117.14 | 1,261 | 4,774,999 | 40,763 | 3,787 |
| 24 Jun 2026 | Sales | Off-plan | Flat · 1 B/R | 89.83 | 967 | 3,779,999 | 42,079 | 3,909 |
Binghatti Skyblade: common questions
Is Binghatti Skyblade delayed?
It is behind plan. Construction was 17.06% complete at the last DLD inspection on 21 April 2026, while its registered timeline (planned completion 30 November 2027) would expect about 43% by then.
When is the handover of Binghatti Skyblade?
The planned completion date registered with Dubai Land Department is 30 November 2027. Handover usually follows completion; the developer confirms the exact date.
How much of Binghatti Skyblade is built?
Construction was 17.06% complete at the last DLD inspection on 21 April 2026, as published by Dubai Land Department.
Where is Binghatti Skyblade located?
Binghatti Skyblade is in Burj Khalifa, Dubai.
Who is the developer of Binghatti Skyblade?
Binghatti Skyblade is developed by Binghatti Developers FZE (DLD developer no. 1051). It is registered with Dubai Land Department as project no. 3725.
Does Binghatti Skyblade have an escrow account?
Yes. Dubai Land Department open data lists escrow account 001582194170301. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in Binghatti Skyblade?
The most recent sale registered with Dubai Land Department was on 19 October 2026 for AED 1,969,999. Across the 71 recorded sales, the average was AED 4,078 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.