Binghatti Rubyphoto: binghatti.comActive
Progress
46.43%
Handover
Escrow
#012918620778

Binghatti Ruby

#3533 · Binghatti Developers FZE · Al Barsha South Fourth · 628 units

More from Binghatti
declared value 220.2M AED data last checked 12 Sept 2026

UB+B + G + 4P +2 Office+ 18 RESIDENTIAL FLOORS + ROOF

Construction progress

46.43% of construction complete · last inspected by DLD 23 Jul 2026

overdue — planned finish was 28 Feb 2026, still at 46.43%

today
inspected 23 Jul 2026
start 1 Jan 2025 est. finish 28 Feb 2026