Binghatti Pointphoto: binghatti.comFinished
Progress
100%
Handover
~ Feb 2022
Escrow
#0011370621020

Binghatti Point

#2203 · Binghatti Developers FZE · Silicon Oasis

More from Binghatti
data last checked 17 Jul 2026

Construction progress

100% of construction complete · last inspected by DLD 3 Feb 2022
inspected 3 Feb 2022
start 1 Mar 2019 est. finish 3 Feb 2022
Average rent 1BR
55,809 AED/yr
12 contracts
Google · this project
4.0
47 reviews