Binghatti Hillviewsphoto: binghatti.comActive
Progress
32.6%
Handover
Escrow
#29166569

Binghatti Hillviews

#3321 · Binghatti Developers FZE · Al Barshaa South Second · 2339 units

More from Binghatti
declared value 859.1M AED data last checked 12 Sept 2026

2B + G + 4P + 37 RESIDENTIAL FLOORS + 1 mech.+ ROOF

Construction progress

32.6% of construction complete · last inspected by DLD 25 Jun 2026

overdue — planned finish was 1 Apr 2026, still at 32.6%

today
inspected 25 Jun 2026
start 1 Oct 2024 est. finish 1 Apr 2026