Binghatti Flare 01photo: binghatti.comActive
Progress
20%
Handover
~ Jul 2027
Escrow
#001582193595601

Binghatti Flare 01

#4006 · Binghatti Developers FZE · Jumeirah Village Triangle

More from Binghatti
data last checked 17 Jul 2026

Construction progress

20% of construction complete · last inspected by DLD 19 Jun 2026

≈27 pts behind the planned pace as of the last inspection

today
inspected 19 Jun 2026
start 15 Jul 2025 est. finish 14 Jul 2027
Google · this project
4.4
27 reviews