photo: binghatti.comUnder constructionDLD developer no. 1051 · Binghatti Developers FZE
Data last checked 29 Oct 2026
More from Binghatti →B + G + 4P + 18 RESIDENTIAL FLOORS + MECH. + ROOF
Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 28 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 53.81 | 579 | 1,229,999 | 22,858 | 2,124 |
| 13 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 60.88 | 655 | 1,100,000 | 18,068 | 1,679 |
| 12 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 60.86 | 655 | 1,316,999 | 21,640 | 2,010 |
| 9 Oct 2026 | Sales | Off-plan | Flat · Studio | 31.33 | 337 | 700,000 | 22,343 | 2,076 |
| 6 Oct 2026 | Sales | Off-plan | Flat · Studio | 31.33 | 337 | 768,999 | 24,545 | 2,280 |
| 5 Oct 2026 | Sales | Off-plan | Flat · Studio | 31.24 | 336 | 766,999 | 24,552 | 2,281 |
| 5 Oct 2026 | Sales | Off-plan | Flat · Studio | 31.23 | 336 | 764,999 | 24,496 | 2,276 |
| 5 Oct 2026 | Sales | Off-plan | Flat · Studio | 31.24 | 336 | 766,999 | 24,552 | 2,281 |
| 5 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 60.86 | 655 | 1,075,000 | 17,663 | 1,641 |
| 3 Oct 2026 | Sales | Off-plan | Flat · Studio | 38.73 | 417 | 700,800 | 18,095 | 1,681 |
| 2 Oct 2026 | Sales | Off-plan | Flat · Studio | 31.33 | 337 | 768,999 | 24,545 | 2,280 |
| 2 Oct 2026 | Sales | Off-plan | Flat · Studio | 31.33 | 337 | 772,999 | 24,673 | 2,292 |
| 1 Oct 2026 | Sales | Off-plan | Flat · Studio | 31.23 | 336 | 765,999 | 24,528 | 2,279 |
| 24 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 60.86 | 655 | 1,316,999 | 21,640 | 2,010 |
| 17 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 60.86 | 655 | 1,000,000 | 16,431 | 1,527 |
Binghatti Etherea: common questions
Is Binghatti Etherea delayed?
It is behind plan. Construction was 7.24% complete at the last DLD inspection on 15 September 2026, while its registered timeline (planned completion 31 December 2027) would expect about 35% by then.
When is the handover of Binghatti Etherea?
The planned completion date registered with Dubai Land Department is 31 December 2027. Handover usually follows completion; the developer confirms the exact date.
How much of Binghatti Etherea is built?
Construction was 7.24% complete at the last DLD inspection on 15 September 2026, as published by Dubai Land Department.
Where is Binghatti Etherea located?
Binghatti Etherea is in Jumeirah Village Circle (JVC), Dubai. Dubai Land Department records it under the Al Barsha South Fourth area.
Who is the developer of Binghatti Etherea?
Binghatti Etherea is developed by Binghatti Developers FZE (DLD developer no. 1051). It is registered with Dubai Land Department as project no. 4303, with 287 units.
Does Binghatti Etherea have an escrow account?
Yes. Dubai Land Department open data lists escrow account 019500000878. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in Binghatti Etherea?
The most recent sale registered with Dubai Land Department was on 28 October 2026 for AED 1,229,999. Across the 73 recorded sales, the average was AED 2,123 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.