Binghatti Elitephoto: binghatti.comActive
Progress
53.25%
Handover
Escrow
#29171035

Binghatti Elite

#3341 · Binghatti Developers FZE · Me'Aisem First · 1745 units

More from Binghatti
declared value 600.0M AED data last checked 12 Sept 2026

4B + G + 2P + 23 RESIDENTIAL FLOORS + ROOF.

Construction progress

53.25% of construction complete · last inspected by DLD 20 Apr 2026

≈34 pts behind the planned pace as of the last inspection

today
inspected 20 Apr 2026
start 30 Nov 2024 est. finish 30 Jun 2026
Google · this project
4.1
34 reviews