Binghatti Crescentphoto: binghatti.comFinished
Progress
100%
Handover
~ Oct 2023
Escrow
#0011370621065

Binghatti Crescent

#2535 · Binghatti Developers FZE · Jumeirah Village Circle

escrow #0011370621065

Escrow bank is not published in DLD open data — verify the escrow agent via Dubai REST before paying into the account.

No further description published for this project.

Construction progress

100% of construction complete · last inspected by DLD 26 Oct 2023
inspected 26 Oct 2023
start 15 Oct 2022 est. finish 26 Oct 2023