photo: reportagegroup.comUnder constructionBianca
DLD developer no. 1277 · REPORTAGE PRIME PROPERTIES L.L.C
Data last checked 29 Oct 2026
653 x G+2+R Townhouses, The project designed to have a concrete structure and block with internal and external finishes.The project designed to have a concrete structure and block with internal and external finishes.
Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 26 Oct 2026 | Gifts | Off-plan | Villa · 2 B/R | 90.64 | 976 | 687,826 | 7,589 | 705 |
| 26 Oct 2026 | Gifts | Off-plan | Villa · 2 B/R | 94.25 | 1,014 | 700,880.11 | 7,436 | 691 |
| 16 Oct 2026 | Sales | Off-plan | Villa · 2 B/R | 90.64 | 976 | 1,466,912 | 16,184 | 1,504 |
| 16 Oct 2026 | Sales | Off-plan | Villa · 2 B/R | 90.64 | 976 | 1,287,000 | 14,199 | 1,319 |
| 15 Oct 2026 | Sales | Off-plan | Villa · 2 B/R | 90.64 | 976 | 1,182,000 | 13,041 | 1,212 |
| 1 Oct 2026 | Sales | Off-plan | Villa · 2 B/R | 90.64 | 976 | 1,020,000 | 11,253 | 1,045 |
| 1 Oct 2026 | Sales | Off-plan | Villa · 2 B/R | 90.64 | 976 | 1,020,000 | 11,253 | 1,045 |
| 1 Oct 2026 | Sales | Off-plan | Villa · 2 B/R | 90.64 | 976 | 1,370,000 | 15,115 | 1,404 |
| 22 Sept 2026 | Sales | Off-plan | Villa · 2 B/R | 91.9 | 989 | 1,320,000 | 14,363 | 1,334 |
| 18 Sept 2026 | Sales | Off-plan | Villa · 4 B/R | 90.64 | 976 | 2,000,000 | 22,065 | 2,050 |
| 12 Sept 2026 | Sales | Off-plan | Villa · 2 B/R | 90.64 | 976 | 1,300,000 | 14,342 | 1,332 |
| 11 Sept 2026 | Sales | Off-plan | Villa · 2 B/R | 90.64 | 976 | 1,250,000 | 13,791 | 1,281 |
| 8 Sept 2026 | Sales | Off-plan | Villa · 4 B/R | 93.79 | 1,010 | 1,750,000 | 18,659 | 1,733 |
| 31 Aug 2026 | Sales | Off-plan | Villa · 2 B/R | 94.25 | 1,014 | 1,170,000 | 12,414 | 1,153 |
| 24 Aug 2026 | Sales | Off-plan | Villa · 2 B/R | 90.64 | 976 | 1,436,029 | 15,843 | 1,472 |
Bianca: common questions
Is Bianca delayed?
It is behind plan. Construction was 56.13% complete at the last DLD inspection on 3 June 2026, while its registered timeline (planned completion 31 December 2026) would expect about 82% by then.
When is the handover of Bianca?
The planned completion date registered with Dubai Land Department is 31 December 2026. Handover usually follows completion; the developer confirms the exact date.
How much of Bianca is built?
Construction was 56.13% complete at the last DLD inspection on 3 June 2026, as published by Dubai Land Department.
Where is Bianca located?
Bianca is in Wadi Al Safa 2, Dubai.
Who is the developer of Bianca?
Bianca is developed by REPORTAGE PRIME PROPERTIES L.L.C (DLD developer no. 1277). It is registered with Dubai Land Department as project no. 2553, with 653 units.
Does Bianca have an escrow account?
Yes. Dubai Land Department open data lists escrow account 994000037096. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in Bianca?
The most recent sale registered with Dubai Land Department was on 16 October 2026 for AED 1,466,912. Across the 42 recorded sales, the average was AED 1,313 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.