Berkeley Square by Prestige Onephoto: prestigeone.aeActive
Progress
3%
Handover
~ Mar 2028
Escrow
#0405920610405

Berkeley Square by Prestige One

#3847 · PRESTIGE LUXE REAL ESTATE DEVELOPMENT L.L.C · Jumeirah Village Circle

More from Prestige One
data last checked 17 Jul 2026

Construction progress

3% of construction complete · last inspected by DLD 25 Jun 2026

≈33 pts behind the planned pace as of the last inspection

today
inspected 25 Jun 2026
start 1 Jul 2025 est. finish 30 Mar 2028