BELLE VIE BY ZIMAYAphoto: zimayaproperties.comActive
Progress
11%
Handover
~ Mar 2028
Escrow
#019500000813

BELLE VIE BY ZIMAYA

#4023 · ZIMAYA PROPERTIES L.L.C · Silicon Oasis

data last checked 17 Jul 2026

Construction progress

11% of construction complete · last inspected by DLD 9 Sept 2026

≈26 pts behind the planned pace as of the last inspection

today
inspected 9 Sept 2026
start 15 Oct 2025 est. finish 31 Mar 2028