photo: sunrisedevelopers.comUnder constructionBellavion by Sunrise
Developer: Sunrise Capital Real Estate Development L.L.C
Deals checked 29 Oct 2026 · project details as of 17 Jul 2026
Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 19 Oct 2026 | Sales | Off-plan | Flat · 2 B/R | 117.23 | 1,262 | 1,757,500 | 14,992 | 1,393 |
| 15 Oct 2026 | Sales | Off-plan | Office · NA | 100.48 | 1,082 | 2,717,000 | 27,040 | 2,512 |
| 14 Oct 2026 | Sales | Off-plan | Office · NA | 157.53 | 1,696 | 4,156,250 | 26,384 | 2,451 |
| 13 Oct 2026 | Sales | Off-plan | Office · NA | 88.84 | 956 | 2,470,000 | 27,803 | 2,583 |
| 13 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 66.96 | 721 | 965,000 | 14,412 | 1,339 |
| 15 Sept 2026 | Sales | Off-plan | Flat · 2 B/R | 152.12 | 1,637 | 1,900,000 | 12,490 | 1,160 |
| 14 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 85.79 | 923 | 1,220,000 | 14,221 | 1,321 |
| 9 Sept 2026 | Sales | Off-plan | Flat · Studio | 36.63 | 394 | 762,300 | 20,811 | 1,933 |
| 26 Aug 2026 | Sales | Off-plan | Flat · 2 B/R | 137.96 | 1,485 | 2,100,000 | 15,222 | 1,414 |
| 17 Aug 2026 | Sales | Off-plan | Flat · 2 B/R | 150.02 | 1,615 | 1,824,000 | 12,158 | 1,130 |
| 17 Aug 2026 | Sales | Off-plan | Flat · 2 B/R | 137.94 | 1,485 | 2,300,000 | 16,674 | 1,549 |
| 17 Aug 2026 | Sales | Off-plan | Flat · 1 B/R | 73.29 | 789 | 1,285,250 | 17,536 | 1,629 |
| 2 Jul 2026 | Sales | Off-plan | Office · NA | 81.73 | 880 | 2,256,000 | 27,603 | 2,564 |
| 2 Jul 2026 | Sales | Off-plan | Flat · 2 B/R | 117.23 | 1,262 | 2,000,000 | 17,060 | 1,585 |
| 2 Jul 2026 | Sales | Off-plan | Flat · 1 B/R | 68.46 | 737 | 1,318,100 | 19,254 | 1,789 |
Bellavion by Sunrise: common questions
Is Bellavion by Sunrise delayed?
It is behind plan. Construction was 10.3% complete at the last DLD inspection on 8 June 2026, while its registered timeline (planned completion 1 December 2027) would expect about 43% by then.
When is the handover of Bellavion by Sunrise?
The planned completion date registered with Dubai Land Department is 1 December 2027. Handover usually follows completion; the developer confirms the exact date.
How much of Bellavion by Sunrise is built?
Construction was 10.3% complete at the last DLD inspection on 8 June 2026, as published by Dubai Land Department.
Where is Bellavion by Sunrise located?
Bellavion by Sunrise is in Jabal Ali First, Dubai.
Who is the developer of Bellavion by Sunrise?
Bellavion by Sunrise is developed by Sunrise Capital Real Estate Development L.L.C. It is registered with Dubai Land Department as project no. 3472.
Does Bellavion by Sunrise have an escrow account?
Yes. Dubai Land Department open data lists escrow account 019500000730. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in Bellavion by Sunrise?
The most recent sale registered with Dubai Land Department was on 19 October 2026 for AED 1,757,500. Across the 71 recorded sales, the average was AED 1,507 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.