BEACH OASIS 2photo: azizidevelopments.comActive
Progress
53.22%
Handover
Escrow
#0800008103002

BEACH OASIS 2

#3043 · AZIZI DEVELOPMENTS L.L.C · Al Hebiah Second · 704 units

More from Azizi
declared value 181.3M AED data last checked 12 Sept 2026

Building 1 (Tower A): 8 F+R ? Residential Apartment Building 2 (Tower B): 8 F+R? Residential Apartment Shared (Basement+ Ground): 2B+G - Residential-Apartment + Commercial-Retail

Construction progress

53.22% of construction complete · last inspected by DLD 7 Sept 2026

overdue — planned finish was 30 Apr 2026, still at 53.22%

today
inspected 7 Sept 2026
start 15 Apr 2024 est. finish 30 Apr 2026