Azurline Residences by MAAS Developersphoto: maas.aeActive
Progress
41.57%
Handover
~ Mar 2027
Escrow
#13309973920002

Azurline Residences by MAAS Developers

#3477 · M A A S Developers L.L.C · Jumeirah Village Circle

data last checked 17 Jul 2026

Construction progress

41.57% of construction complete · last inspected by DLD 30 Apr 2026

on pace — ≈18 pts behind the plan as of the last inspection

today
inspected 30 Apr 2026
start 1 Jan 2025 est. finish 31 Mar 2027
Google · this project