Azizi Venice 15photo: azizidevelopments.comActive
Progress
0%
Handover
~ May 2027
Escrow
unavailable

Azizi Venice 15

#3741 · AZIZI DEVELOPMENTS L.L.C · Madinat Al Mataar

More from Azizi
registry detail unavailable — outside current DLD window data last checked 17 Jul 2026

Construction progress

0% of construction complete · last inspected by DLD 6 May 2025

on pace with the planned timeline

last DLD inspection was 1.4 years ago — this figure may no longer reflect the site's actual progress

today inspected 6 May 2025
start 2 May 2025 est. finish 30 May 2027