azizi venice 12photo: azizidevelopments.comActive
Progress
15.29%
Handover
~ Sept 2027
Escrow
unavailable

azizi venice 12

#3318 · AZIZI DEVELOPMENTS L.L.C · Madinat Al Mataar

More from Azizi
registry detail unavailable — outside current DLD window data last checked 17 Jul 2026

Construction progress

15.29% of construction complete · last inspected by DLD 22 Apr 2026

≈37 pts behind the planned pace as of the last inspection

today
inspected 22 Apr 2026
start 25 Sept 2024 est. finish 25 Sept 2027