Active
Progress
90.8%
Handover
~ Mar 2027
Escrow
#10174999920268

Azizi Riviera 62

#3619 · AZIZI DEVELOPMENTS L.L.C · Meydan One

More from Azizi
data last checked 17 Jul 2026

Construction progress

90.8% of construction complete · last inspected by DLD 30 Jul 2026

on pace with the planned timeline

today
inspected 30 Jul 2026
start 13 Mar 2025 est. finish 13 Mar 2027