photo: damacproperties.comUnder constructionAYKON CITY 3
Developer: Damac Canal One Property Development L.L.C
Deals checked 29 Oct 2026 · project details as of 17 Jul 2026
Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 23 Oct 2026 | Gifts | Off-plan | Flat · 3 B/R | 138.46 | 1,490 | 2,000,002.02 | 14,445 | 1,342 |
| 22 Oct 2026 | Sales | Off-plan | Flat · Studio | 33.24 | 358 | 825,000 | 24,819 | 2,306 |
| 12 Oct 2026 | Sales | Off-plan | Flat · 2 B/R | 102.71 | 1,106 | 2,549,960 | 24,827 | 2,306 |
| 8 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 72.01 | 775 | 1,420,000 | 19,719 | 1,832 |
| 6 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 71.67 | 771 | 2,000,000 | 27,906 | 2,593 |
| 16 Sept 2026 | Gifts | Off-plan | Flat · 1 B/R | 71.59 | 771 | 2,000,004.7 | 27,937 | 2,595 |
| 1 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 71.91 | 774 | 2,067,560 | 28,752 | 2,671 |
| 1 Sept 2026 | Sales | Off-plan | Flat · 2 B/R | 106.73 | 1,149 | 3,137,696 | 29,398 | 2,731 |
| 18 Aug 2026 | Sales | Off-plan | Flat · 1 B/R | 73.1 | 787 | 1,976,000 | 27,031 | 2,511 |
| 14 Aug 2026 | Sales | Off-plan | Flat · 2 B/R | 106.39 | 1,145 | 2,785,000 | 26,177 | 2,432 |
| 12 Aug 2026 | Sales | Off-plan | Flat · 2 B/R | 127.83 | 1,376 | 4,523,310 | 35,385 | 3,287 |
| 3 Aug 2026 | Gifts | Off-plan | Flat · 1 B/R | 73.16 | 787 | 2,165,006.88 | 29,593 | 2,749 |
| 3 Aug 2026 | Gifts | Off-plan | Flat · 1 B/R | 73.39 | 790 | 2,250,003.57 | 30,658 | 2,848 |
| 3 Aug 2026 | Gifts | Off-plan | Flat · 1 B/R | 69.67 | 750 | 2,045,001.84 | 29,353 | 2,727 |
| 23 Jul 2026 | Sales | Off-plan | Flat · 2 B/R | 105.32 | 1,134 | 2,860,466 | 27,160 | 2,523 |
AYKON CITY 3: common questions
Is AYKON CITY 3 delayed?
It is behind plan. Construction was 31.35% complete at the last DLD inspection on 12 April 2026, while its registered timeline (planned completion 30 December 2027) would expect about 79% by then.
When is the handover of AYKON CITY 3?
The planned completion date registered with Dubai Land Department is 30 December 2027. Handover usually follows completion; the developer confirms the exact date.
How much of AYKON CITY 3 is built?
Construction was 31.35% complete at the last DLD inspection on 12 April 2026, as published by Dubai Land Department.
Where is AYKON CITY 3 located?
AYKON CITY 3 is in Business Bay, Dubai.
Who is the developer of AYKON CITY 3?
AYKON CITY 3 is developed by Damac Canal One Property Development L.L.C. It is registered with Dubai Land Department as project no. 2200.
Does AYKON CITY 3 have an escrow account?
Yes. Dubai Land Department open data lists escrow account 0405690787202. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in AYKON CITY 3?
The most recent sale registered with Dubai Land Department was on 22 October 2026 for AED 825,000. Across the 42 recorded sales, the average was AED 2,609 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.