Avenue Park Towersphoto: wasl.aeActive
Progress
2.79%
Handover
~ Dec 2028
Escrow
#0205256122110

Avenue Park Towers

#3337 · PARK 1 L.L.C · Al Kifaf

data last checked 17 Jul 2026

Construction progress

2.79% of construction complete · last inspected by DLD 19 Feb 2026

on pace — ≈13 pts behind the plan as of the last inspection

today
inspected 19 Feb 2026
start 1 Aug 2025 est. finish 31 Dec 2028
Google · this project
3.0
2 reviews