photo: aman.comUnder constructionAman Residences Dubai
Developer: Blackwood Development L.L.C
Deals checked 29 Oct 2026 · project details as of 17 Jul 2026
Location
No Google rating available for this project yet.
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 11 Aug 2026 | Sales | Off-plan | Flat · 2 B/R | 355.46 | 3,826 | 54,736,514 | 153,988 | 14,306 |
| 11 Aug 2026 | Sales | Off-plan | Flat · 2 B/R | 355.29 | 3,824 | 57,555,304 | 161,995 | 15,050 |
| 22 Jul 2026 | Sales | Off-plan | Flat · 5 B/R | 931.01 | 10,021 | 166,077,188 | 178,384 | 16,572 |
| 29 Apr 2026 | Sales | Off-plan | Flat · 3 B/R | 552.21 | 5,944 | 83,188,690.62 | 150,647 | 13,996 |
| 27 Apr 2026 | Sales | Off-plan | Flat · 2 B/R | 355.46 | 3,826 | 49,074,116 | 138,058 | 12,826 |
| 21 Apr 2026 | Sales | Off-plan | Flat · 3 B/R | 552.25 | 5,944 | 70,041,472 | 126,829 | 11,783 |
| 10 Apr 2026 | Sales | Off-plan | Flat · 5 B/R | 931.01 | 10,021 | 171,036,254 | 183,710 | 17,067 |
| 9 Apr 2026 | Sales | Off-plan | Flat · 2 B/R | 355.46 | 3,826 | 54,250,000 | 152,619 | 14,179 |
| 6 Apr 2026 | Sales | Off-plan | Flat · 4 B/R | 552.2 | 5,944 | 70,238,323 | 127,197 | 11,817 |
| 6 Apr 2026 | Sales | Off-plan | Flat · 2 B/R | 355.29 | 3,824 | 58,253,515.74 | 163,960 | 15,232 |
| 2 Apr 2026 | Sales | Off-plan | Flat · 3 B/R | 552.21 | 5,944 | 79,496,805 | 143,961 | 13,374 |
| 27 Mar 2026 | Sales | Off-plan | Flat · 2 B/R | 355.29 | 3,824 | 55,668,244 | 156,684 | 14,556 |
| 27 Mar 2026 | Sales | Off-plan | Flat · 3 B/R | 552.21 | 5,944 | 76,801,998 | 139,081 | 12,921 |
| 27 Mar 2026 | Sales | Off-plan | Flat · 3 B/R | 552.25 | 5,944 | 70,041,472 | 126,829 | 11,783 |
| 26 Mar 2026 | Sales | Off-plan | Flat · 6 B/R | 2,898.63 | 31,201 | 356,232,500 | 122,897 | 11,418 |
Aman Residences Dubai: common questions
Is Aman Residences Dubai delayed?
It is behind plan. Construction was 0.92% complete at the last DLD inspection on 10 August 2026, while its registered timeline (planned completion 31 December 2028) would expect about 31% by then.
When is the handover of Aman Residences Dubai?
The planned completion date registered with Dubai Land Department is 31 December 2028. Handover usually follows completion; the developer confirms the exact date.
How much of Aman Residences Dubai is built?
Construction was 0.92% complete at the last DLD inspection on 10 August 2026, as published by Dubai Land Department.
Where is Aman Residences Dubai located?
Aman Residences Dubai is in Jumeirah Second, Dubai.
Who is the developer of Aman Residences Dubai?
Aman Residences Dubai is developed by Blackwood Development L.L.C. It is registered with Dubai Land Department as project no. 3461.
Does Aman Residences Dubai have an escrow account?
Yes. Dubai Land Department open data lists escrow account 0205908368504. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in Aman Residences Dubai?
The most recent sale registered with Dubai Land Department was on 11 August 2026 for AED 54,736,514. Across the 20 recorded sales, the average was AED 13,609 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.