Altonphoto: nshama.aeUnder construction

Alton

DLD project no. 3685 · Al Yelayiss 2

Progress
5.15%
DLD inspected 18 Aug 2026
Handover
~ May 2028
Est. finish 31 May 2028
Escrow
#4031224702173091
Registered escrow account
Google rating
—

DLD developer no. 1162 · NSHAMA PROPERTIES OWNED BY NSHMI DEVELOPMENT ONE PERSON COMPANY L.L.C

Deals checked 29 Oct 2026 · project details as of 17 Jul 2026

More from nshama →
DLDConstruction inspection
5.15% of construction complete · last inspected by DLD 18 Aug 2026

≈26 pts behind the planned pace as of the last inspection

today
inspected 18 Aug 2026
start 1 Nov 2025 est. finish 31 May 2028

Alton: common questions

Is Alton delayed?

It is behind plan. Construction was 5.15% complete at the last DLD inspection on 18 August 2026, while its registered timeline (planned completion 31 May 2028) would expect about 31% by then.

When is the handover of Alton?

The planned completion date registered with Dubai Land Department is 31 May 2028. Handover usually follows completion; the developer confirms the exact date.

How much of Alton is built?

Construction was 5.15% complete at the last DLD inspection on 18 August 2026, as published by Dubai Land Department.

Where is Alton located?

Alton is in Al Yelayiss 2, Dubai.

Who is the developer of Alton?

Alton is developed by NSHAMA PROPERTIES OWNED BY NSHMI DEVELOPMENT ONE PERSON COMPANY L.L.C (DLD developer no. 1162). It is registered with Dubai Land Department as project no. 3685.

Does Alton have an escrow account?

Yes. Dubai Land Department open data lists escrow account 4031224702173091. Always confirm the account with the developer or in the Dubai REST app before paying.

What are recent sale prices in Alton?

The most recent sale registered with Dubai Land Department was on 22 October 2026 for AED 1,183,888. Across the 32 recorded sales, the average was AED 1,664 per sq ft.

Answers are generated from Dubai Land Department open data shown on this page.