Developer: Acube Abodes Real Estate Development L.L.C
Deals checked 29 Oct 2026 · project details as of 17 Jul 2026
Location
No Google rating available for this project yet.
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 12 Oct 2026 | Sales | Off-plan | Flat · Studio | 48.96 | 527 | 725,944.18 | 14,827 | 1,378 |
| 8 Oct 2026 | Sales | Off-plan | Flat · 1 B/R | 69.23 | 745 | 987,045.5 | 14,257 | 1,325 |
| 8 Oct 2026 | Sales | Off-plan | Flat · 2 B/R | 102.5 | 1,103 | 1,400,000 | 13,659 | 1,269 |
| 2 Jul 2026 | Sales | Off-plan | Flat · 2 B/R | 108.79 | 1,171 | 1,476,385.91 | 13,571 | 1,261 |
| 24 Jun 2026 | Sales | Off-plan | Flat · Studio | 48.93 | 527 | 743,161 | 15,188 | 1,411 |
| 24 Jun 2026 | Sales | Off-plan | Flat · Studio | 48.96 | 527 | 689,646 | 14,086 | 1,309 |
| 24 Jun 2026 | Sales | Off-plan | Flat · 2 B/R | 108.79 | 1,171 | 1,438,105 | 13,219 | 1,228 |
| 27 Apr 2026 | Sales | Off-plan | Flat · 2 B/R | 108.83 | 1,171 | 1,647,011 | 15,134 | 1,406 |
| 27 Apr 2026 | Sales | Off-plan | Flat · 2 B/R | 108.86 | 1,172 | 1,571,449 | 14,436 | 1,341 |
| 10 Apr 2026 | Sales | Off-plan | Flat · 1 B/R | 69.26 | 746 | 1,148,755 | 16,586 | 1,541 |
| 17 Feb 2026 | Sales | Off-plan | Flat · 1 B/R | 69.26 | 746 | 981,163 | 14,166 | 1,316 |
| 16 Feb 2026 | Sales | Off-plan | Flat · 1 B/R | 69.26 | 746 | 1,000,000 | 14,438 | 1,341 |
| 12 Feb 2026 | Sales | Off-plan | Flat · 1 B/R | 69.23 | 745 | 1,016,062 | 14,677 | 1,364 |
| 12 Feb 2026 | Sales | Off-plan | Flat · Studio | 41.82 | 450 | 631,279 | 15,095 | 1,402 |
| 10 Feb 2026 | Sales | Off-plan | Flat · Studio | 48.93 | 527 | 868,334 | 17,746 | 1,649 |
Altair 52: common questions
Is Altair 52 delayed?
It is behind plan. Construction was 10.06% complete at the last DLD inspection on 24 September 2026, while its registered timeline (planned completion 31 December 2027) would expect about 37% by then.
When is the handover of Altair 52?
The planned completion date registered with Dubai Land Department is 31 December 2027. Handover usually follows completion; the developer confirms the exact date.
How much of Altair 52 is built?
Construction was 10.06% complete at the last DLD inspection on 24 September 2026, as published by Dubai Land Department.
Where is Altair 52 located?
Altair 52 is in Dubai South, Dubai.
Who is the developer of Altair 52?
Altair 52 is developed by Acube Abodes Real Estate Development L.L.C. It is registered with Dubai Land Department as project no. 3657.
Does Altair 52 have an escrow account?
Yes. Dubai Land Department open data lists escrow account 0800008398002. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in Altair 52?
The most recent sale registered with Dubai Land Department was on 12 October 2026 for AED 725,944. Across the 19 recorded sales, the average was AED 1,387 per sq ft.