Altair 52photo: acubeabodesrealty.comUnder construction

Altair 52

DLD project no. 3657 · Dubai South

Progress
10.06%
DLD inspected 24 Sept 2026
Handover
~ Dec 2027
Est. finish 31 Dec 2027
Escrow
#0800008398002
Registered escrow account
Google rating
—

Developer: Acube Abodes Real Estate Development L.L.C

Deals checked 29 Oct 2026 · project details as of 17 Jul 2026

DLDConstruction inspection
10.06% of construction complete · last inspected by DLD 24 Sept 2026

≈27 pts behind the planned pace as of the last inspection

today
inspected 24 Sept 2026
start 31 Dec 2025 est. finish 31 Dec 2027

Location

Altair 52: common questions

Is Altair 52 delayed?

It is behind plan. Construction was 10.06% complete at the last DLD inspection on 24 September 2026, while its registered timeline (planned completion 31 December 2027) would expect about 37% by then.

When is the handover of Altair 52?

The planned completion date registered with Dubai Land Department is 31 December 2027. Handover usually follows completion; the developer confirms the exact date.

How much of Altair 52 is built?

Construction was 10.06% complete at the last DLD inspection on 24 September 2026, as published by Dubai Land Department.

Where is Altair 52 located?

Altair 52 is in Dubai South, Dubai.

Who is the developer of Altair 52?

Altair 52 is developed by Acube Abodes Real Estate Development L.L.C. It is registered with Dubai Land Department as project no. 3657.

Does Altair 52 have an escrow account?

Yes. Dubai Land Department open data lists escrow account 0800008398002. Always confirm the account with the developer or in the Dubai REST app before paying.

What are recent sale prices in Altair 52?

The most recent sale registered with Dubai Land Department was on 12 October 2026 for AED 725,944. Across the 19 recorded sales, the average was AED 1,387 per sq ft.

Answers are generated from Dubai Land Department open data shown on this page.