photo: emaar.comUnder constructionDLD developer no. 1224 · DUBAI CREEK HARBOUR L.L.C
Deals checked 29 Oct 2026 · project details as of 17 Jul 2026
More from Emaar →Location
This project on Google
Sale register covers the last ~3 months.
| Date | Type | Segment | Unit | Size m² | Size sqft | Price AED | AED/m² | AED/sqft |
|---|---|---|---|---|---|---|---|---|
| 24 Sept 2026 | Sales | Off-plan | Flat · 1 B/R | 71.58 | 770 | 2,011,888 | 28,107 | 2,611 |
| 14 Sept 2026 | Sales | Off-plan | Flat · 3 B/R | 171.7 | 1,848 | 4,267,888 | 24,857 | 2,309 |
| 11 Aug 2026 | Sales | Off-plan | Flat · 2 B/R | 135.02 | 1,453 | 3,380,004 | 25,033 | 2,326 |
| 13 May 2026 | Sales | Off-plan | Flat · 1 B/R | 70.37 | 757 | 1,770,814 | 25,164 | 2,338 |
| 1 May 2026 | Sales | Off-plan | Flat · 3 B/R | 171.7 | 1,848 | 4,323,888 | 25,183 | 2,340 |
| 27 Apr 2026 | Sales | Off-plan | Flat · 2 B/R | 135.02 | 1,453 | 3,286,888 | 24,344 | 2,262 |
| 21 Apr 2026 | Sales | Off-plan | Flat · 1 B/R | 71.96 | 775 | 1,932,888 | 26,861 | 2,495 |
| 17 Apr 2026 | Sales | Off-plan | Flat · 3 B/R | 171.7 | 1,848 | 4,149,888 | 24,169 | 2,245 |
| 17 Apr 2026 | Sales | Off-plan | Flat · 1 B/R | 71.38 | 768 | 1,871,888 | 26,224 | 2,436 |
| 9 Apr 2026 | Sales | Off-plan | Flat · 2 B/R | 135.02 | 1,453 | 3,292,888 | 24,388 | 2,266 |
| 8 Apr 2026 | Sales | Off-plan | Flat · 3 B/R | 171.7 | 1,848 | 4,141,888 | 24,123 | 2,241 |
| 2 Apr 2026 | Sales | Off-plan | Flat · 2 B/R | 133.34 | 1,435 | 3,227,888 | 24,208 | 2,249 |
| 1 Apr 2026 | Sales | Off-plan | Flat · 3 B/R | 171.7 | 1,848 | 4,196,888 | 24,443 | 2,271 |
| 1 Apr 2026 | Sales | Off-plan | Flat · 2 B/R | 135.02 | 1,453 | 3,279,888 | 24,292 | 2,257 |
| 31 Mar 2026 | Sales | Off-plan | Flat · 3 B/R | 171.7 | 1,848 | 4,133,888 | 24,076 | 2,237 |
Albero: common questions
Is Albero delayed?
Not by DLD figures. Construction was 11% complete at the last DLD inspection on 2 July 2026, in line with or ahead of its registered timeline (about 24% expected by then, planned completion 30 September 2029).
When is the handover of Albero?
The planned completion date registered with Dubai Land Department is 30 September 2029. Handover usually follows completion; the developer confirms the exact date.
How much of Albero is built?
Construction was 11% complete at the last DLD inspection on 2 July 2026, as published by Dubai Land Department.
Where is Albero located?
Albero is in Al Khairan First, Dubai.
Who is the developer of Albero?
Albero is developed by DUBAI CREEK HARBOUR L.L.C (DLD developer no. 1224). It is registered with Dubai Land Department as project no. 3609.
Does Albero have an escrow account?
Yes. Dubai Land Department open data lists escrow account 0205668118509. Always confirm the account with the developer or in the Dubai REST app before paying.
What are recent sale prices in Albero?
The most recent sale registered with Dubai Land Department was on 24 September 2026 for AED 2,011,888. Across the 33 recorded sales, the average was AED 2,330 per sq ft.
Answers are generated from Dubai Land Department open data shown on this page.