AL WALEED w.s 1photo: alwaleedrealestate.comActive
Progress
18.27%
Handover
~ Feb 2027
Escrow
#0205837920904

AL WALEED w.s 1

#3712 · Al Waleed Development L.L.C · Dubai Land Residence Complex

data last checked 17 Jul 2026

Construction progress

18.27% of construction complete · last inspected by DLD 18 Jun 2026

≈44 pts behind the planned pace as of the last inspection

today
inspected 18 Jun 2026
start 1 May 2025 est. finish 28 Feb 2027