ABJAR TOWER

DLD project no. 109 · —

Progress
0.75%
Handover
—
Planned finish 1 Dec 2013
Escrow
#4498000540
Registered escrow account
Google rating
—

Developer: Khuyool Investments (L.L.C)

Deals checked 29 Oct 2026 · project details as of 17 Jul 2026

DLDConstruction inspection
0.75% of construction complete

overdue — planned finish was 1 Dec 2013, still at 0.75%

today
start 1 Aug 2009 est. finish 1 Dec 2013
Google · this project
0 reviews

ABJAR TOWER: common questions

Is ABJAR TOWER delayed?

Dubai Land Department lists ABJAR TOWER as cancelled.

Who is the developer of ABJAR TOWER?

ABJAR TOWER is developed by Khuyool Investments (L.L.C). It is registered with Dubai Land Department as project no. 109.

Does ABJAR TOWER have an escrow account?

Yes. Dubai Land Department open data lists escrow account 4498000540. Always confirm the account with the developer or in the Dubai REST app before paying.

Answers are generated from Dubai Land Department open data shown on this page.