4B Livingphoto: hse-realty.comActive
Progress
90.95%
Handover
Escrow
#19328864

4B Living

#3089 · H S E Realty Real Estate L.L.C · International City Ph 2 & 3

data last checked 17 Jul 2026

Construction progress

90.95% of construction complete · last inspected by DLD 4 Feb 2026

overdue — planned finish was 30 Aug 2025, still at 90.95%

today
inspected 4 Feb 2026
start 27 May 2024 est. finish 30 Aug 2025