Cancelled

PARAMOUNT HOTEL-JUMEIRAH WATERFRONT

#1361 · Damac Development(L L C) · —

Progress
7%
DLD inspected 16 Nov 2017
Handover
—
Est. finish 25 Dec 2017
Escrow
#15875026
Registered escrow account
Google rating
—

Data last checked 17 Jul 2026

More from Damac →
DLDConstruction inspection
7% of construction complete · last inspected by DLD 16 Nov 2017

≈90 pts behind the planned pace as of the last inspection

last DLD inspection was 8.9 years ago — this figure may no longer reflect the site's actual progress

today inspected 16 Nov 2017
start 10 Jan 2014 est. finish 25 Dec 2017
Google · this project
0 reviews