CAPRIA EASTphoto: ghafwoods.comUnder construction

CAPRIA EAST

#3524 · Majid Al Futtaim Ghaf Woods L.L.C · Wadi Al Safa 4

Progress
0.94%
DLD inspected 23 Jun 2026
Handover
~ May 2029
Est. finish 15 May 2029
Escrow
#0205872406711
Registered escrow account
Google rating
—

Data last checked 17 Jul 2026

More from Majid Al Futtaim →
DLDConstruction inspection
0.94% of construction complete · last inspected by DLD 23 Jun 2026

on pace — ≈20 pts behind the plan as of the last inspection

today
inspected 23 Jun 2026
start 15 Sept 2025 est. finish 15 May 2029
Google · this project
0 reviews