Cancelled
Progress
3.4%
Handover
—
Escrow
#4498002577

INDIGO OPTIMA 2

#1111 · Mars Properties Investment Limited · —

data last checked 17 Jul 2026

Construction progress

3.4% of construction complete

overdue — planned finish was 15 Dec 2011, still at 3.4%

today
start 24 Mar 2008 est. finish 15 Dec 2011