Manhattan 2 by SDphoto: samanadevelopers.comActive
Progress
21.24%
Handover
~ Nov 2026
Escrow
#001582177382001

Manhattan 2 by SD

#2802 · SAMANA STAR REAL ESTATE DEVELOPMENT L.L.C · Al Barsha South Fourth · 193 units

More from Samana
declared value 68.0M AED data last checked 22 Sept 2026

G + 3P + 16 Residential + Retail

Construction progress

21.24% of construction complete · last inspected by DLD 17 Sept 2026

≈74 pts behind the planned pace as of the last inspection

today
inspected 17 Sept 2026
start 1 Apr 2024 est. finish 1 Nov 2026
Google · this project
5.0