Verano By Prescottphoto: prescott.aeActive
Progress
32.61%
Handover
~ Dec 2026
Escrow
#200824099

Verano By Prescott

#3339 · PRESCOTT REAL ESTATE DEVELOPMENT L.L.C · Al Hebiah Second · 269 units

More from Prescott
declared value 101.2M AED data last checked 12 Sept 2026

1B+G+7Floor+Roof.The project designed to have a concrete structure and block with internal and external finishes.

Construction progress

32.61% of construction complete · last inspected by DLD 2 Jul 2026

≈39 pts behind the planned pace as of the last inspection

today
inspected 2 Jul 2026
start 30 Mar 2025 est. finish 31 Dec 2026
Google · this project
3.4
8 reviews