Lexingtonphoto: nshama.aeActive
Progress
0.03%
Handover
~ Sept 2027
Escrow
#4031224702173074

Lexington

#3364 · NSHAMA PROPERTIES OWNED BY NSHMI DEVELOPMENT ONE PERSON COMPANY L.L.C · Al Yelayiss 2

More from nshama
data last checked 17 Jul 2026

Escrow bank is not published in DLD open data — verify the escrow agent via Dubai REST before paying into the account.

No further description published for this project.

Construction progress

0.03% of construction complete · last inspected by DLD 3 Feb 2026

≈31 pts behind the planned pace as of the last inspection

today
inspected 3 Feb 2026
start 5 May 2025 est. finish 30 Sept 2027