Hillcrestphoto: nshama.aeActive
Progress
38.36%
Handover
~ Jun 2027
Escrow
#4031224702173068

Hillcrest

#3211 · NSHAMA PROPERTIES OWNED BY NSHMI DEVELOPMENT ONE PERSON COMPANY L.L.C · Al Yelayiss 2

More from nshama
data last checked 17 Jul 2026

Construction progress

38.36% of construction complete · last inspected by DLD 17 Sept 2026

≈28 pts behind the planned pace as of the last inspection

today
inspected 17 Sept 2026
start 3 Mar 2025 est. finish 30 Jun 2027