SUNSET BAY THREE BY IMTIAZphoto: imtiaz.aeActive
Progress
38.2%
Handover
~ Mar 2027
Escrow
#1031226743829005

SUNSET BAY THREE BY IMTIAZ

#3604 · IMTIAZ SUNSET REAL ESTATE DEVELOPMENT L.L.C · Palm Deira

Escrow bank is not published in DLD open data — verify the escrow agent via Dubai REST before paying into the account.

No further description published for this project.

Construction progress

38.2% of construction complete · last inspected by DLD 25 Jun 2026

≈25 pts behind the planned pace as of the last inspection

today
inspected 25 Jun 2026
start 20 Mar 2025 est. finish 20 Mar 2027