TRIA BY DEYAARphoto: deyaar.aeActive
Progress
93.4%
Handover
Escrow
#001582280702301

TRIA BY DEYAAR

#2403 · DEYAAR DEVELOPMENT (P.J.S.C) · Silicon Oasis

More from Deyaar
data last checked 17 Jul 2026

Escrow bank is not published in DLD open data — verify the escrow agent via Dubai REST before paying into the account.

No further description published for this project.

Construction progress

93.4% of construction complete · last inspected by DLD 3 Aug 2026

overdue — planned finish was 30 Jun 2025, still at 93.4%

today
inspected 3 Aug 2026
start 1 Aug 2022 est. finish 30 Jun 2025
Google · this project
★★★★★★★★★★