NEEM AT PARK FIVEphoto: deyaar.aeActive
Progress
10.63%
Handover
~ Dec 2027
Escrow
#001582174791701

NEEM AT PARK FIVE

#3496 · DEYAAR DEVELOPMENT (P.J.S.C) · Dubai Production City

More from Deyaar
data last checked 17 Jul 2026

Escrow bank is not published in DLD open data — verify the escrow agent via Dubai REST before paying into the account.

No further description published for this project.

Construction progress

10.63% of construction complete · last inspected by DLD 10 Jun 2026

≈28 pts behind the planned pace as of the last inspection

today
inspected 10 Jun 2026
start 1 Jul 2025 est. finish 1 Dec 2027
Google · this project
★★★★★★★★★★
0 reviews